Stacker / Reclaimer Installation2019-07-08T11:01:41-07:00

Project Description

STACKER/RECLAIMER INSTALLATION

Installation of a Greenfield chip unloading, storage (stacking), reclaiming, and feed system.

  • Unloading – two 75′ Phelps Industries truck dump systems feeding three Dimisa conveyors (930′ total length).
  • Stacker/Reclaimer – FMW 360 degree stacker/reclaimer capable of stacking 6 million cubic feet of wood chips.
  • Feed System – one 874′ under/above ground Dimisa conveyor from the reclaimer to the existing chip silos.

SERVICES PROVIDED

  • Site preparation including installation of underground drainage and fire systems, dewatering, excavation for foundations, and paving
  • Installation of 6700 yards of concrete and 275 tons of rebar for equipment foundations
  • Fabrication and erection of 500 tons of structural steel for equipment
  • Installation of 7500 lineal feet of service piping
  • Installation of 300 lineal feet of underground tunnel
  • Mechanical installation of equipment
  • Fabrication and installation of miscellaneous platforms and structural supports
  • Erection of masonry unit substation building and operators building
  • Mechanical and piping tie-ins to existing facility
  • Commissioning and start-up support

PROJECT STATISTICS

  • On schedule
  • Worked 90,000 safe hours