Oxygen De-Lignification2019-07-08T11:01:22-07:00

Project Description

OXYGEN DE-LIGNIFICATION

Field assembly of ASME pressure vessel along with fabrication and installation of process piping, pumps, and mixer.

SERVICES PROVIDED

  • Field assembly of 220 ft. tall ASME vessel – three pieces with field joints
  • Top section piece was 110,000 lbs. The pick was using 308 ton Demag crane.
  • Fabricate and install 1,000 lineal feet of stainless steel process piping.
  • Process piping included 24″, 16″, 12″, and 8″
  • Installation of new dilution pump and mixer

PROJECT STATISTICS

  • On schedule
  • Zero lost time accidents

Project Details

Industries:

Location:

Client:

Weyerhaeuser