Project Description
OXYGEN DE-LIGNIFICATION
Field assembly of ASME pressure vessel along with fabrication and installation of process piping, pumps, and mixer.
SERVICES PROVIDED
- Field assembly of 220 ft. tall ASME vessel – three pieces with field joints
- Top section piece was 110,000 lbs. The pick was using 308 ton Demag crane.
- Fabricate and install 1,000 lineal feet of stainless steel process piping.
- Process piping included 24″, 16″, 12″, and 8″
- Installation of new dilution pump and mixer
PROJECT STATISTICS
- On schedule
- Zero lost time accidents