No. 5 Boiler Conversion 2017-04-30T11:31:09+00:00

Project Description

NO. 5 BOILER CONVERSION

Plant owner engaged Greenberry for this critical boiler conversion project based on its 30+ years of experience.

SERVICES PROVIDED

  • Project management and coordination
  • Pipe fabrication and installation, including steam and pressure piping
  • All structural steel fabrication and erection
  • 100% of civil scope
  • Mechanical installation
  • Subcontractor management, included instrumentation, insulation, scaffolding and crane service

PROJECT STATISTICS

  • On schedule and under budget
  • 45-man shutdown over 21 days working around the clock

Project Details

Client:

Georgia Pacific

Location: