Corporate Headquarters

600 SE Maritime Ave. Suite 190
Vancouver, WA 98661

Search

Projects

Mt. Poso Plant Conversion

Owner

Mt. Poso Cogeneration

Location

Bakersfield, CA

Industry

Power & Energy

Services

Industrial Fabrication

Project Overview

Greenberry was the general contractor for the installation of a Greenfield biomass unloading, storage (stacking), reclaiming, and feed system. The new system contained the following items:

  • Unloading three receiving hoppers (two for live bottom trucks, one 75′ industrial truck dump) feeding five conveyors (1500′ total length).
  • Stacker/Reclaimer capable of stacking 4 million cubic feet of biomass.
  • Feed System five (1350′ total length) from the reclaimer to the Day Bin.
  • Fuel Feed System two chain conveyors (100′ total length), four screw conveyors, and two Rotary Valves.

Project Highlights

  • On schedule
  • Worked 100,000+ safe hours

Services performed include:

  • Subcontract management of site preparation including installation of underground utilities, fire systems, excavation for foundations, and paving
  • Installation of 3700 yards of concrete and 150 tons of rebar for equipment foundations
  • Fabrication and erection of 700 tons of structural steel for equipment
  • Installation of 7500 lineal feet of service piping including, firewater, utility water, and compressed air
  • Installation of 2500 lineal feet of hydraulic and lubrication tubing.
  • Demolition of existing coal feed equipment.
  • Modifications to the existing structures including four new structural towers to support new fuel feed equipment.
  • Subcontract management of the Electrical scope including all power, control, and instrumentation wiring, and the installation of MCC’s, PLC’s, and transformers (two 1500KVA, one 1000KVA) for three new MCC rooms.
  • Installed and tested over three hundred instruments
  • Mechanical, electrical, and piping tie-ins to existing facility
  • Commissioning and start-up support
  • Day bin modifications including the removal of its existing cone bottom, installing 1250 square feet of stainless lining, and installing a new flat bottom with structural steel reinforcement.
  • Mechanical installation of equipment

Awards & Recognition

Share This Project