Project Description
MELTER INSTALLATION
Xerox relied on Greeberry’s ability to install process equipment while their plant remained in full operation.
SERVICES PROVIDED
- Provided project management and coordination
- Installed augers and pneumatic conveyor system
- Managed four subcontractors
- Fabricated and installed stainless steel jacketed piping
- Set two melter tanks on load cells
- Set all mechanical equipment
- Relocated baghouse from inside building to roof with all piping
- Performed all work while plant was in operation
- Performed a number of short evening and weekend outages to work with production schedule
- Polished orbital welded tubing for vacuum system
- Performed extensive work on hot oil system
PROJECT STATISTICS
- Under budget