Stacker / Reclaimer Installation

Owner

Weyerhaeuser

Location

Springfield, OR

Industry

Pulp & Paper

Services

Industrial Fabrication

Project Overview

Installation of a Greenfield chip unloading, storage (stacking), reclaiming, and feed system.

  • Unloading two 75′ Phelps Industries truck dump systems feeding three Dimisa conveyors (930′ total length).
  • Stacker/Reclaimer FMW 360 degree stacker/reclaimer capable of stacking 6 million cubic feet of wood chips.
  • Feed System one 874 under/above ground Dimisa conveyor from the reclaimer to the existing chip silos.

 

Project Highlights

Services provided include:

  • Site preparation including installation of underground drainage and fire systems, dewatering, excavation for foundations, and paving
  • Installation of 6700 yards of concrete and 275 tons of rebar for equipment foundations
  • Fabrication and erection of 500 tons of structural steel for equipment
  • Installation of 7500 linear feet of service piping
  • Installation of 300 linear feet of underground tunnel
  • Mechanical installation of equipment
  • Fabrication and installation of miscellaneous platforms and structural supports
  • Erection of masonry unit substation building and operators building
  • Mechanical and piping tie-ins to existing facility
  • Commissioning and start-up support